The condominium association at The Sanctuary at Alexandra Place along Tampa's Bayshore Boulevard has filed a lawsuit against the tower's developers and contractor, alleging that unfinished, "defective" work has caused issues in the building.
|
The Sanctuary at Alexandra Place |
Bradley Arant Boult
Cummings, attorney for Taub, declined comment. Plaza's
attorney and Jones did not respond to requests for comment.
It is not uncommon for condo associations to sue developers
over alleged construction issues, said Gregg Hutt, a
construction litigator and partner at Trenam in Tampa.
Some in the industry argue that chapter 558 of the Florida
statutes, which governs defects in condo construction,
encourages associations to take a litigious approach. Luxury
apartment developers will sometimes place restrictions on a
property's deed that forbid a conversion to condominiums for
10 years, which is when the statute of limitations runs out
for construction defects.
Hutt said the defects are often remedied.
As part of the turnover process, "there is a report that
gets prepared by design professionals, typically engineers
of various disciplines, that go and inspect the building,"
he said. "Typically, I've seen it as the association and
engineers or other design professionals go and inspect the
building. They prepare a report, and based on that report,
they bring the claim."
A similar report was prepared for the separate lawsuit in
2021 between Plaza and Taub regarding the tower. That
lawsuit, also in Hillsborough County Circuit Court, is
ongoing and relates to various claims of nonpayment and
incomplete work by both parties. Taub claims Plaza
"improperly stopped work and abandoned the project prior to
completion of the project," according to court documents.
Plaza claims Taub did not pay in a timely manner; instead,
Taub paid subcontractors directly.
Sponsored Content
Court documents show Plaza also requested "an extension of
time and compensation for delays on the project due to
complications created by the Covid-19 pandemic. Taub refused
to grant Plaza any extension of time or pay Plaza anything
for this delay."
At the turnover meeting with Sanctuary condo owners, Brian
Taub "apologized to the unit owners who were present for
failing to properly complete construction and for failing to
deliver the final product" that was promised, the new
lawsuit claims. Additionally, Taub agreed to hire a
completion contractor — however, that has not been done, the
condo association claims.
Eric Appleton, attorney for the condo association, said the
association's directors are optimistic.
"The leadership of Taub Entities and Plaza Construction need
to step up and pay for the damages incurred by the
association and its unit owners. If they do not do that
immediately, we are confident that the court will hold them
accountable," Appleton said in a statement.
The association has included many counts in its lawsuit,
including breach of statutory warranties for "failing to
design, construct, and deliver The Sanctuary in compliance
with the Florida Building Code." Others include negligence,
breach of fiduciary duty, and deceptive and unfair trade
practices.
Units at The Sanctuary are around 4,000 square feet and were
priced from $2.3 million to over $5 million. A three-story
penthouse sold in 2021 for $7.2 million, the highest price
ever paid for a condominium at that time in Tampa.