Construction woes continue to plague Palm Beach Gardens condo complex

Article Courtesy of  The Palm Beach Post

By Jodie Wagner

Published August 9, 2019
 

PALM BEACH GARDENS — Nearly two years after work began to repair extensive water damage to all 30 buildings at the San Matera condominium community, yellow caution tape seals off portions of the 100-acre complex, while construction debris sits in piles in the parking lots.
   

In April, the project’s contractor, Fort Myers-based Florida Structural Group, walked off the job in a payment dispute, according to homeowners, and work has come to a standstill.

Residents have been left waiting and wondering who is going to finish a job that was made necessary when water intrusion caused by design and construction defects damaged many of the complex’s 676 units.

Work is not complete on any of the buildings, and some remain without stucco in the midst of hurricane season.

“Principal external wall material of many of the buildings is Tyvek, not stucco as intended,” said Michael Dan, a San Matera resident who owns four units in the complex just north of The Gardens Mall.

Work to repair leaky roofs, poorly pitched porches and other problems began a year after a $22.5 million settlement was reached in 2016 between San Matera The Gardens Condominium Association and insurers for builder Kolter Homes and dozens of subcontractors.

Problems surfaced almost immediately after construction was completed in 2005.

Scaffolding equipment is removed from the San Mateo condominium complex in Palm Beach Gardens after a contractor hired to fix water intrusionproblems walked off the job in April. Construction has yet to resume.


 

In addition to roof defects that caused water leaks, engineers found concrete porches weren’t sloped properly, metal lath and stucco were incorrectly installed, windows failed, and areas that required a single truss instead had two that weren’t connected at the apex. Light poles didn’t have sufficient concrete foundations, and concrete flooring slabs were cracked.
 

As a result, water seeped through walls, roofs, windows and sliding glass doors.

“Everybody had a window that had something wrong with it,” Dan said.

After a lawsuit was filed and settled, Florida Structural Group was contracted to begin repairs on the buildings, the complex’s management company said. Work proceeded for about 18 months until April 10, when workers stopped showing up.

“We were supposed to have somebody come and do some work, and they didn’t come,” Dan said. “And then we saw everyone leave. There was not a single worker on site the Monday morning afterwards. We asked what was going on.”

Dan and other San Matera residents said answers were hard to come by from the association’s board and management team.

Eugene Sears, who owns two units in San Matera, said residents weren’t made aware of any problems with Florida Structural Group prior to the work stoppage, and weren’t given any information for at least two weeks afterward.

“We had to start a letter-writing campaign before the board finally provided us with some information, and it was no more than what we had already found out from the court documents or figured out on our own,” he said.

Information still isn’t being provided in a timely manner, some residents say, but board President Maryann Morrison denies there is a lack of communication between management and residents. Public meetings are held as often as possible, she said, and updates are provided when there is new information to give.

“They are getting information,” she said of residents, some of whom have aired grievances through a San Matera Owners Facebook group started by Dan. “We’ve had everybody who’s ever done work on the property into meetings.”

Morrison said the board has spent the past several months working to secure bids from construction companies interested in completing the project, and has brought on new legal counsel to protect residents’ interests. The matter is in litigation — again.

“The construction has been a hindrance in the improvement of our community,” Morrison said. “Who would have guessed this would have happened a second time around?”

A resolution should be coming soon, she said.

In a July 11 email from management, residents were told the board is negotiating with one construction company on a contract to complete repairs. There is no timetable, according to management, but the board is looking to start work as soon as possible.

“We’re trying to rebuild this community,” Morrison said. “We’re trying to rebuild little by little. ... We’re trying to beautify. We don’t want this reputation for being the eyesore of the neighborhood.”