Two years after a $21 million assessment
for repairs outraged owners at a Brickell condo complex, the
association is suing its contractor, alleging it overbilled
and left work undone.
The 1060 Brickell Condominium Association, which represents
592 units at two 45-story towers, sued American Construction
& Engineering, saying it tacked on — and received — funds
for work and materials it didn’t provide and then filed two
fraudulent liens saying it’s owed additional payment,
according to the complaint.
The property consists of 576 residential and 16 commercial
units at the 1050 Brickell and 1060 Brickell buildings in
Miami.
The suit is the latest flare-up at a complex that has
been consumed by conflict in recent years.
On a macro level across South Florida, many condo owners are
pushing back against costly repair projects that have become
mandatory since the Surfside collapse prompted stricter
structural safety laws.
A growing number of owners say their boards, engineers and
contractors are exploiting the safety rules to rush
projects, pad repair work, include unnecessary cosmetic
items and saddle unit owners with hefty assessments.
At the 1060 Brickell association, tensions trace back to
2024, when then-boardmembers put forth the planned $21
million special assessment for repairs, with many unit
owners questioning the need. Many pointed out that the
towers, completed in 2008, were only 16 years old at the
time — far short of the 30-year trigger for a structural
recertification requirement.
A group of unit owners led a hard-fought battle to oust the
former board, which had imposed the assessment.
Even though the board was replaced, current President
Dorinda Spahr confirmed to The Real Deal that the assessment
remained in place.
Spahr said the board recall spared the complex from
potential pricey change orders that were in store and would
have pushed the cost closer to $48 million.
Miami-based American Construction & Engineering, or ACE, had
been hired for the work, including replacement of damaged
stucco, repairs of the concrete, post-tension cables and
cracks, waterproofing, painting, glass and glazing work,
according to the association’s complaint. But ACE’s two
construction liens filed in August for nearly $3 million are
“willfully exaggerated” and include amounts not even due
under ACE’s contracts with the association, the suit says.
For the 1050 Brickell tower, ACE was overpaid by $1.5
million, yet it claimed it’s due roughly this amount in one
of its liens, while ACE’s 1060 Brickell lien for about $1.5
million overstates the amount the contract is owed by
roughly $840,000, according to the complaint.
The Miami-Dade Circuit Court complaint, filed last Thursday,
raises claims for breach of contract, fraudulent claim of
lien and slander of title.
ACE and its owner, Peter Anta, didn’t return requests for
comment.
A troubled history
Spahr and two other owners sued last year over a canceled
November 2024 board election. Although Spahr ran for the
board at the time, the association disqualified her,
claiming she was overdue on payments, though she was late on
levies tied to the use of common space storage, for which
owners don’t receive invoices, TRD reported at the time,
citing court filings.
Unit owners filed arbitration petitions with the state’s
department of business and professional regulation and led
their own recall effort, twice voting to replace the former
board.
In the fall of last year, a Miami-Dade judge issued an order
in a separate suit involving 1060 Brickell for the former
board to turn over association control and records.
Separately, married couple Jessica Bergman and Antonio
Sevillano, who are unit owners, sued the association in late
2024 over the $21 million assessment, claiming the board
imposed it without the unit owner approval required by the
declaration, according to the complaint.
According to court filings, the association said it based
the assessments on its engineer’s structural integrity
reserve study report, while the unit owners’ engineer
disputed the urgency for the work. After the board was
turned over, that case settled privately.
Bergman and Sevillano’s complaint alleged the board’s vote
on the assessment collection mandated unit owners pay a
quarter of their share upfront and then pay the balance in
nine quarterly installments.
About two or three installments are left on the assessment,
Spahr said.