The Palm Beach Code Enforcement Board decided to not fine the Claridges Condominium over two code violation cases related to two air conditioning units installed without the town's approval. But the board warned it wouldn’t be as lenient at a later meeting, if progress isn’t made toward permitting the new equipment.
|
The South End Claridge Condominium has been caught up in two code violation cases, after the cooling towers were installed at the property's two buildings without the town's approval. |
During the Aug. 21 code board meeting,
Gavigan said the condominium association had hired an
architect and was drafting documents required for the design
review and permit application process for the building at
3456 S Ocean Blvd. That led the code board to defer that
building's fine-consideration case to its Dec. 18 meeting.
But when the two cases returned in December, the
documentation required for the permit review process was
still pending, according to code officers.
At the latest meeting, Gavigan said that all required
documentation had been completed, save for the surveys of
the property and cooling towers.
He said the delays were caused by the surveyors, as they
only measured the elevation of the cooling towers.
Considering the project would require the approval of both
the Architectural Commission and Town Council, he asked for
a 60-day or 90-day delay on the daily running fines.
But the patience of some board members was wearing thin,
considering the extended amount of time given to the
condominium.
“It strikes me as being wise to consider having a fine now,
and maybe at a future date, they can come back for a fine
consideration once they’ve completed” the permit process,
alternate board member John Cohen said.
But Member Chris Larmoyeux thought a fine delay was worth
considering, since the project had completed nearly all the
required documents needed for the review process, save for
the surveyor's elevation study.
Gavigan also noted that while the cooling towers were
installed without the proper permitting, the variance
associated with their height was due to the code’s outdated
height limits for roof top mechanical equipment.
Board Chair Martin Klein agreed that the zoning code is
outdated. But that still doesn’t change the fact that the
cooling towers were installed without the town’s approval,
he told Gavigan.
“I’d be much happier if you told me, you filed all the
papers necessary for the variance, and it was just a matter
of waiting for the Town Council to act,” Klein said.
When Board Member Harris Fried made a motion to hit the
condominium with a $250 daily running fine for each code
violation case, his colleague Chris Larmoyeux pushed back.
Though the condominium had faced delays getting the required
documents, they have made notable efforts to get the process
for these cooling towers’ approval started, he said.
Moreover, unlike other code violations under review,
representatives for the condominium had attended each
meeting and delivered updates to the board each time.
“I believe very strongly a fine at this moment is
inappropriate,” he said.
Larmoyeux proposed to give the project a month to complete
the survey work. If no progress is made by then, then the
board can consider a daily-running fine, he said.
That proposal convinced the board, including his colleague
Fried.
